التعليقات على: القوة القاهرة ( Force Majeure ) في فيديك 1999الأحمر https://arabic.cmguide.org/?p=289 كل ما تحتاجه للنجاح الذاتي والمهني.. Sun, 16 Feb 2014 09:19:18 +0000 hourly 1 https://wordpress.org/?v=6.4.8 بواسطة: AKRAM https://arabic.cmguide.org/?p=289&cpage=1#comment-58 Tue, 01 Mar 2011 13:22:08 +0000 http://cmguide.org/arabic/?p=289#comment-58 what if the force majeure did not prevent the contractor fom completing his works , but he suffered only from delay and additional costs??r

]]>
بواسطة: نائل الداري https://arabic.cmguide.org/?p=289&cpage=1#comment-37 Sun, 27 Jun 2010 09:55:16 +0000 http://cmguide.org/arabic/?p=289#comment-37 what about the bankruptcy of the subcontractor or one of the suppliers , does it form ground for extension of time and force majeure 

]]>